GENERAL

  • This instruction details the procedure to be followed to ensure that all the elements of the assurance system are operating effectively.
  • PLANNING

  • The Quality Audit Plan. The QE is to prepare a 12 monthly quality audit plan. The plan takes the form of the matrix (see figure 1) and ensures that all the elements of the quality assurance system are regularly audited.
  • Line


    Ser  Sect  Month
    Jan  Feb  Mar  Apr  May  Jun  Jul  Aug  Sep  Oct  Nov  Dec
    Work Instruction
    10  11  12  3
    (a)  (b)  (c)  (d)  (e)  (f)  (g)  (h)  (i)  (j)  (k)  (l)  (m)  (n)
    Dept 1  D
    Dept 2  E
    Dept 3  F
    Dept 4  G

    Auditors:

    A = IC Dept 1, B = IC Dept 2, C = IC Dept 3, D = IC Dept 4, E = 2IC Dept 1, F = 2IC Dept 2,

    G = 2IC Dept 3, H = 2IC Dept 4.

    Auditor A will conduct any audits that can not be conducted due to leave or courses.

    Fig 1 Example of Quality Audit Plan Matrix
    Line

    ANNEX A

    QUALITY AUDIT REPORT

    Dept Audited: Dept Head:                                                                            Activity Audited:

    Compliance / Non-compliance / Deficiency (Delete and comment as necessary), details:

    Auditor: (Signature) Date:

    Corrective Action is as follows:

    Target Date (Dept Head):                                                                            Dept Head: (Signature) Date:

    FOLLOW UP AUDIT

    The corrective action has / has not been completed by the new target date.  Auditor: (Signature) Date:

    Comment (Dept Head):

    Dept Head: (Signature) Date:                                                                      QE: (Signature) Date: Text starts here